电缆桥架作为电力与信号传输系统的骨架支撑,其安装质量直接影响线路运行与使用寿命。从建筑结构适配到电气性能保障,每个环节都需严格遵循技术规范。本文将从工程实践角度,系统梳理电缆桥架安装的核心注意事项。
As the backbone support of power and signal transmission systems, the installation quality of cable trays directly affects the safety and service life of the line operation. From structural adaptation to electrical performance assurance, every aspect must strictly adhere to technical specifications. This article will systematically sort out the core precautions for cable tray installation from the perspective of engineering practice.
一、安装前期规划要点
1、 Key points of pre installation planning
路径优化设计
Path optimization design
需结合建筑图纸进行三维走线模拟,避免与消防喷淋、空调风管等设施冲突。采用BIM技术进行碰撞检测,可使管线交叉率降低。对于长距离桥架,每30米需设置伸缩节,以补偿热胀冷缩变形。
Three dimensional wiring simulation should be carried out in conjunction with architectural drawings to avoid conflicts with facilities such as fire sprinklers and air conditioning ducts. Using BIM technology for collision detection can reduce the intersection rate of pipelines. For long-distance cable trays, expansion joints should be installed every 30 meters to compensate for thermal expansion and contraction deformation.
荷载精准核算
Accurate calculation of load
静态荷载需考虑电缆自重及桥架本体重量,电缆填充率不宜超过截面积的40%。动态荷载则需预留检修人员活动余量,按集中荷载2kN进行校核。
Static loads should consider the weight of the cable and the weight of the bridge body, and the cable filling rate should not exceed 40% of the cross-sectional area. For dynamic loads, it is necessary to reserve enough space for maintenance personnel to move around, and verify according to a concentrated load of 2kN.
环境适配性评估
Environmental adaptability assessment
在腐蚀性环境需选用316L不锈钢或热浸锌桥架,盐雾试验480小时后,普通镀锌桥架腐蚀面积达15%,而316L不锈钢桥架腐蚀面积低于1%。对于潮湿区域,桥架底部需设置排水孔,孔径5-8mm为宜。
In corrosive environments, 316L stainless steel or hot-dip galvanized cable trays should be selected. After 480 hours of salt spray testing, the corrosion area of ordinary galvanized cable trays reaches 15%, while the corrosion area of 316L stainless steel cable trays is less than 1%. For damp areas, drainage holes with a diameter of 5-8mm should be installed at the bottom of the bridge.
二、安装过程质量控制
2、 Quality control during installation process
基础固定规范
Basic fixed specifications
混凝土结构采用膨胀螺栓固定时,需使用M10以上螺栓,植入深度不小于70mm。单根M12膨胀螺栓抗拉强度达6kN,可满足常规安装需求。对于钢结构,优先采用焊接固定,焊缝高度需大于母材厚度。
When using expansion bolts to fix concrete structures, M10 or above bolts should be used with an implantation depth of not less than 70mm. The tensile strength of a single M12 expansion bolt can reach 6kN, which can meet conventional installation requirements. For steel structures, welding fixation is preferred, and the height of the weld seam should be greater than the thickness of the base metal.
桥架连接工艺
Bridge connection process
连接片需使用配套镀锌螺栓,紧固力矩控制在12-15N·m。螺栓松动会导致接触电阻增加,引发局部过热。对于跨接接地,需确保跨接导线截面积不小于4mm²,且连接可靠。
The connecting piece needs to use matching galvanized bolts, with a tightening torque controlled at 12-15N · m. Loose bolts can increase contact resistance and cause local overheating. For jumper grounding, it is necessary to ensure that the cross-sectional area of the jumper wire is not less than 4mm² and the connection is reliable.
弯曲半径控制
Bending radius control
水平弯通需满足小弯曲半径要求,多芯电缆弯曲半径为电缆外径的12倍。垂直弯通需设置导缆装置,避免电缆在重力作用下产生侧压力。
Horizontal bending must meet the minimum bending radius requirement, and the bending radius of multi-core cables is 12 times the outer diameter of the cable. Vertical bending requires the installation of a cable guide device to avoid lateral pressure on the cable under the action of gravity.
三、特殊场景处理方案
3、 Special scenario handling plan
防火封堵实施
Fire sealing implementation
穿越防火分区时,需采用防火枕与无机堵料复合封堵。3小时耐火极限封堵系统可使背火面温度升幅控制在140℃以内。对于电缆井,每层楼板处需做防火隔断。
When passing through fire compartments, it is necessary to use fire-resistant pillows and inorganic blocking materials for composite sealing. The 3-hour fire resistance limit sealing system can control the temperature rise of the backfire surface within 140 ℃. For cable shafts, fire-resistant partitions need to be installed at each floor slab.
电磁屏蔽措施
Electromagnetic shielding measures
在电磁敏感区域,需采用镀锌钢板封闭桥架,1.5mm厚钢板可使电磁屏蔽效能提升。接地导线需与桥架全长可靠连接,形成法拉第笼效应。
In electromagnetic sensitive areas, galvanized steel plates should be used to enclose the cable tray, and a 1.5mm thick steel plate can improve the electromagnetic shielding efficiency. The grounding wire needs to be reliably connected to the entire length of the bridge to form the Faraday cage effect.
振动环境防护
Vibration environment protection
对于泵房、车间等振动场所,需安装弹性支架,某振动控制工程的实践表明,橡胶减震垫可使振动传递率降低。电缆需采用蛇形敷设,预留振动补偿余量。
For vibration sites such as pump rooms and workshops, elastic supports need to be installed. The practice of a vibration control project has shown that rubber shock absorbers can reduce the vibration transmission rate. The cable needs to be laid in a serpentine pattern, with reserved vibration compensation allowance.
四、验收与维护标准
4、 Acceptance and maintenance standards
外观检查要点
Key points for appearance inspection
桥架本体需无变形、镀层脱落,某质检机构的抽检数据显示,锌层厚度不足会导致锈蚀风险增加。连接螺栓需齐全紧固,缺失率不得超过2%。
The bridge body needs to be free from deformation and peeling of the coating. According to sampling data from a quality inspection agency, insufficient zinc layer thickness can increase the risk of corrosion. The connecting bolts must be fully tightened, and the missing rate should not exceed 2%.
电气性能测试
Electrical performance testing
接地电阻需小于4Ω,某电气检测中心的测试表明,采用等电位连接可使跨步电压降低。绝缘电阻测试需使用500V兆欧表,测量值应大于10MΩ。
The grounding resistance should be less than 4 Ω. Tests conducted by an electrical testing center have shown that using equipotential connections can reduce step voltage. The insulation resistance test requires the use of a 500V megohmmeter, and the measured value should be greater than 10M Ω.
运行维护规范
Operation and maintenance standards
每季度进行一次巡检,检查连接部位温升。某运维公司的红外测温数据显示,异常温升通常早于故障发生。对于露天桥架,需在春季前检查防水性能,清理排水通道。
Conduct a comprehensive inspection every quarter, with a focus on checking the temperature rise at the connection points. The infrared temperature measurement data of a certain operation and maintenance company shows that abnormal temperature rise usually occurs before the fault occurs. For outdoor cable trays, it is necessary to check the waterproof performance and clean the drainage channels before spring.
电缆桥架安装是涉及多学科知识的系统工程,需从设计、施工到验收建立全周期质量控制体系。通过科学规划路径、严格过程管控、针对性处理特殊场景,可确保桥架系统长期稳定运行。随着智能监测技术的发展,如光纤测温、振动监测等新技术的应用,桥架运维正朝着预防性维护方向演进,这对保障电力传输具有重要意义。
The installation of cable trays is a multidisciplinary system engineering that requires the establishment of a full cycle quality control system from design, construction to acceptance. Through scientific path planning, strict process control, and targeted handling of special scenarios, the long-term stable operation of the bridge system can be ensured. With the development of intelligent monitoring technology, such as the application of new technologies such as fiber optic temperature measurement and vibration monitoring, bridge operation and maintenance are evolving towards preventive maintenance, which is of great significance for ensuring the safety of power transmission.
本文由济南电缆桥架友情奉献.更多有关的知识请点击:http://www.sddlqj.cn我们将会对您提出的疑问进行详细的解答,欢迎您登录网站留言.
This article is a friendly contribution from Shandong Cable Bridge For more information, please click: http://www.sddlqj.cn We will provide detailed answers to your questions. You are welcome to log in to our website and leave a message
电缆桥架作为电力传输系统的重要支撑结构,其质量直接关系到电路与设备稳定运行。山东作为工业大省,各类厂房、高层建筑及市政工程中大量使用电缆桥架,若存在质量隐患,可能引发短路、火灾甚大规模停电等