济南电缆桥架:钢制槽式桥架200*100全费用成本单价分析表

文章来源:https://www.sddlqj.cn/   作者:电缆桥架厂家发布时间:2025-09-18 浏览次数:1

返回:常见问题

  一、施工工艺流程1、梯架、托盘和槽盒全长不大于30m时,不应少于2处与保护导体可靠连接;全长大于30m时,应每隔20m~30m应增加一个连接点,起始端和终点端均应可靠接地。2、直线段钢制电缆桥架长度超过30米、铝合金或者玻璃钢制电缆桥架长度超过15米设有伸缩节。3、桥架穿越墙体及楼板,应用不燃材料封堵;穿越防火分区桥架内必须做防火封堵。4、室外安装桥架安装高度不能低于积雪、积水高度,同时考虑选用防水型盖板,进出室外桥架、线槽,室内须高于室外,防止雨水流入室内。5、电缆出入电缆沟、电气竖井、建筑物,配电(控制)柜、台、箱处以及管子管口处等部位应采取防火或密封措施。二、项目特征①材质、类型:钢制槽式桥架;②规格及型号:200*100;③ 施工内容:组对、焊接或螺栓固定、弯头、三通或四通、盖板、隔板、附件安装等其它完成该项目全部内容。梯级式桥架-001

  1、 When the total length of the ladder frame, pallet, and trough box is not more than 30m, there should be no less than 2 reliable connections with the protective conductor; When the total length is greater than 30m, a connection point should be added every 20m~30m, and both the starting and ending ends should be reliably grounded. 2. Expansion joints are installed for steel cable trays with a length exceeding 30 meters in straight sections and for aluminum alloy or fiberglass cable trays with a length exceeding 15 meters. 3. Bridge passing through walls and floors should be sealed with non combustible materials; Fire sealing must be done inside the bridge frame passing through the fire compartment. 4. The installation height of outdoor cable trays should not be lower than the height of snow and accumulated water. At the same time, waterproof cover plates should be considered. For outdoor cable trays and trunking, the indoor height should be higher than the outdoor height to prevent rainwater from flowing into the indoor area. 5. Fire prevention or sealing measures should be taken for cable entry and exit in cable trenches, electrical shafts, buildings, distribution (control) cabinets, platforms, boxes, and pipe openings. 2、 Project features ① Material and type: Steel trough bridge frame; ② Specification and model: 200 * 100; ③ Construction content: assembly, welding or bolt fixing, elbows, tees or tees, cover plates, partitions, accessory installation, and other completion of the entire project.

  三、单价组价分析

  3、 Unit price group price analysis

  1、直接费

  1. Direct cost

  ①人工费 :26.6元/m;

  ① Labor cost: 26.6 yuan/m;

  ② 材料费:45.6元/m(含项目特征中所有材料);

  ② Material cost: 45.6 yuan/m (including all materials in the project characteristics);

  ③机械及其它费:0.97元/m;

  ③ Mechanical and other expenses: 0.97 yuan/m;

  直接费小计:73.17元/m。

  Subtotal of direct expenses: 73.17 yuan/m.

  2、管理费按直接费的6%:4.39元/m。

  2. The management fee is 6% of the direct fee: 4.39 yuan/m.

  3、利润按直接费的5%:3.66元/m。

  3. Profit is calculated at 5% of direct expenses: 3.66 yuan/m.

  4、税费按直接费、管理费、利润和的3%:2.44元/m。

  4. Taxes and fees are calculated at a rate of 3% of direct fees, management fees, and profits: 2.44 yuan/m.

  5、全费用成本单价约:83.66元/m。

  5. The total cost unit price is approximately 83.66 yuan/m.

  本文由  济南电缆桥架  友情奉献.更多有关的知识请点击  http://www.sddlqj.cn/   真诚的态度.为您提供为的服务.更多有关的知识我们将会陆续向大家奉献.敬请期待.

  This article is a friendly contribution from Jinan Cable Bridge For more related knowledge, please click http://www.sddlqj.cn/ Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Coming soon.

工程案例 / Case Show
  • 济南火车站 济南火车站
  • 曲阜孔子文化会展中心 曲阜孔子文化会展中心
  • 山东工艺美院 山东工艺美院
  • 公安厅服务展示 公安厅服务展示